Neshaminy/Trenton Line Derailment
Design And Construction Support
Client: Southeastern Pennsylvania Transportation Authority
Location: Trevose, PA
Value: $500k (Construction)
Gannett Fleming provided emergency detailed design and construction
support services for the reconstruction of two miles of catenary
and a portal that was destroyed by a CSXT freight train derailment.
On-site field support was provided during an entire 96-hour work
window to assure the Railroad would be put back in service as
soon as possible.
The project involved one route mile of existing two-track, steel
portal frame catenary structures that supported two mainline
catenary systems, crossover catenary, transmission wires, and
signal cables
The existing catenary system was completely torn down between
air breaks (including the crossover) when the freight train derailed
and demolished catenary structure 21/4. GFT&RS was on site
the following morning with a structure design that would accommodate
a quick construction schedule. Within hours, construction began
on the new catenary structure and a temporary support system
to support the catenary. Trolley Wire profiles were designed
as messenger wires were being installed. The hanger tabulations
provided by GFT&RS aided in expediting the catenary construction.
Initially, only the main line tracks were restored to service.
Full-time construction supervision was provided by GFT&RS
to address construction issues.
Following service restoration, we provided a design to replace
the destroyed crossover wire, as well as design for an additional
new crossover wire to facilitate a universal interlocking at
this location.
Services Provided:
- Structure Design
- Catenary Design
- On-Site Construction Support
- New Interlocking
Special Features:
- Two-Mile Catenary Reconstruction
- 96-Hour Design and Construction Window
- Construction by SEPTA Force Account and Contractor
|